Engineering Permits

Occupancy Permit

To use or occupy a building, you must first obtain an occupancy permit from the city government. The same is required when you change the existing use or occupancy classification of a building or any of its portion.

Applicants should have the following documents:

 

1.       Approved Building Permit

 

2.       Certificate of completion signed and sealed by professionals

 

3.       Two (2) photos of the building (front and sides)

 

VC Biz Bilis: Secure an Occupancy Permit

1. Fill up application form from the City Engineer’s Office (CEO), 3/F Bulwagang Geronimo Angeles, Valenzuela City Hall.

2. Submit accomplished form and all other required documents to the CEO. [Allow seven (7) working days for evaluation, processing and approval.]

3.  After seven (7) working days, secure the order of payment from the CEO and pay the corresponding fees at the City Treasurer's Office, G/F Bulwagang Geronimo Angeles, Valenzuela City Hall.

4. Present the official receipt of payment to the CEO and claim the occupancy permit.